Onboarding: RS Testing - Capacity & Performance Test (CPT)
Purpose: Testing system capacity and performance under load.
What is Tested:
-
Ability to process the expected daily trade volume, multiplied by a predefined performance factor.
-
Confirmation that performance standards are met without degradation.
What KOR Does
-
Reviews the tests submitted by the Client.
-
Assists the Client in determining the appropriate volume of testing.
-
Identifies and implements any necessary system adjustments based on testing results.
What the Client Does
-
Submits the agreed testing volumes within the timelines provided by KOR.
Shared Environment Clients
-
Because the environment cannot be reset on demand without affecting other clients, all UTIs must be modified to ensure they do not match production-reported UTIs when backload testing begins.
Estimated Duration:
-
Typically 1 to 5 days.
Can be done before, after, or in parallel with Historical Data UAT